simple_temporal_networks

This library provides the stn_protocol protocol and the stn object for Simple Temporal Networks (STNs). It is a metric substrate for temporal reasoning, e.g., Temporal ATMS libraries. It reuses the intervals library for concrete Allen relation views.

States are opaque ground terms. Updates return a new state without changing the original, allowing independent networks and branching histories. All successfully returned states are consistent. Time-point labels are distinct ground terms, compared by term identity; for example, 1 and 1.0 name different time-points. The reference label zero is reserved and denotes time zero. It is added automatically and must not be supplied to new/2.

API documentation

Open the ../../apis/library_index.html#simple-temporal-networks link in a web browser.

Loading

To load this library, load its loader.lgt file:

| ?- logtalk_load(simple_temporal_networks(loader)).

Testing

To test this library, load its tester.lgt file:

| ?- logtalk_load(simple_temporal_networks(tester)).

Metric model

An input constraint(X, Y, Delta) denotes:

time(Y) - time(X) =< Delta

Delta must be a finite integer or float. A directed edge from X to Y therefore supplies an upper difference bound, not an earliest time. Shortest-path distance d(X,Y) is the tightest upper bound on Y - X. For consistent networks:

difference_bounds(X,Y) = [-d(Y,X), d(X,Y)]
earliest(T) = -d(T,zero)
latest(T)   =  d(zero,T)

There is no implicit assumption that non-reference time-points are non-negative. Missing directed paths yield the symbolic bound positive_infinity; negating that bound yields negative_infinity. These atoms are not arithmetic values and must not be passed to is/2. Self-distances and both bounds of zero are zero. A consistent network may have one-sided or fully unbounded windows.

Bellman-Ford with initially zero potentials for every node detects negative cycles, including components disconnected from zero. A consistent graph is then closed using Floyd-Warshall with fresh matrices for successive intermediate nodes. No destructive term updates are used.

API overview

Public modes, argument names, failure conditions, and explanation formats are documented in stn_protocol.lgt using mode/2 and info/2 directives.

  • new/2, add_time_points/3: Construct a network or append fresh time-points

  • remove_time_points/3: Remove time-points and all incident source constraints, rebuilding once

  • time_points/2, constraints/2, consistent/1: Inspect a library-created state

  • schedule/2: Return one finite feasible time assignment

  • earliest_schedule/2: Return the componentwise earliest assignment when all lower bounds are finite

  • add_constraint/5-6: Add one upper difference bound, optionally returning its ID

  • add_constraints/3-4: Atomically add a batch, optionally returning its IDs

  • try_add_constraints/4: Return an updated state or an identified negative-cycle witness

  • remove_constraints/3: Remove source constraints by ID and rebuild once

  • distance/4-5: Query an upper difference bound, optionally with one supporting path

  • earliest/3, latest/3, bounds/4: Query absolute time bounds

  • difference_bounds/5: Query both relative difference bounds

  • entails/4-5: Test an upper difference bound, optionally with a supporting path

  • can_precede/3, must_precede/3: Test possible or entailed strict precedence

  • can_precede_or_equal/3, must_precede_or_equal/3: Test possible or entailed non-strict precedence

  • window_interval/3: Export a finite non-degenerate marginal window as numeric i(Start,End)

  • event_interval/4: Export a fixed positive-duration event as numeric i(Start,End)

  • window_relation/4: Classify finite non-degenerate marginal windows

  • event_relation/6: Classify two events whose four endpoints are fixed

Malformed public arguments, unknown time-point labels, and invalid weights fail without binding input variables. State arguments must be states returned by this API. Arithmetic evaluation and representation errors propagate rather than being interpreted as temporal contradictions. Empty update batches and empty time-point extensions return the original state. Retraction accepts a list of positive integer IDs, ignoring missing IDs and duplicate requests.

remove_time_points/3 accepts a ground list of labels and removes those points together with every source constraint whose endpoint is removed. Missing labels and duplicate requests are ignored; a request containing zero fails atomically. Requests removing no existing point return the original state, while isolated points are removed even when no source changes. Surviving node/source order, source IDs, and the next source ID are preserved. Queries for removed points fail because those labels are no longer declared.

Schedules

schedule(STN, Schedule) returns one finite assignment as time(Point, Value) terms in declaration order, including time(zero, 0) first. It also assigns finite values to isolated points, disconnected components, and points with unbounded absolute windows. The original state and source identifiers are unchanged. Repeated calls on the same state select the same assignment.

The assignment uses each cached closure column’s minimum finite distance, then shifts all values so the reference point is zero. In exact arithmetic, these minima are shortest-path potentials from an implicit source with zero-weight edges to every point. Normalization preserves their differences. Every retained source inequality is checked after normalization using backend arithmetic. A violation raises evaluation_error(stn_numerical_inconsistency); non-finite arithmetic raises evaluation_error(float_overflow). No tolerance or numerical repair is applied, and floating-point results remain approximate.

This selects one assignment, not an enumeration, optimization, execution policy, or necessarily a non-negative or globally earliest schedule. An unconstrained point need not receive zero when another component anchors the reference normalization. See the schedule and numeric limitations below.

earliest_schedule(STN, Schedule) instead returns each point’s finite earliest absolute bound in the same format and declaration order, with time(zero, 0) first. Every declared point must have a finite lower bound; finite upper bounds are not required. An unbounded lower bound causes failure without binding the output. No artificial floor is added, and the state and source identifiers are unchanged.

This reads the reference column of the cached closure and negates each distance to zero. In exact arithmetic, the resulting assignment jointly attains every coordinate’s minimum, including bounds propagated through correlated points. It uses the same retained-source validation as schedule/2; floating-point feasibility and minimality are not exact-real guarantees.

For example, propagate a lower bound through a duration constraint while choosing the earliest value of an independently anchored point:

| ?- stn::new([a,b,c], STN0),
     stn::add_constraints(STN0, [
       constraint(a,zero,-5), constraint(b,a,-2),
       constraint(c,zero,-1), constraint(zero,c,3)
     ], STN),
     stn::earliest_schedule(STN, Schedule).
Schedule = [time(zero,0),time(a,5),time(b,7),time(c,1)].

Sources and explanations

Every accepted source receives a monotonically allocated positive integer ID. constraints/2 returns constraint(Id,X,Y,Delta) terms in insertion order, including parallel, redundant, and equal-weight constraints. Synthetic zero diagonals are not source constraints. Removing a stronger source can therefore restore a surviving weaker bound or a tied alternative support. Removed IDs are not reused in accepted descendant states.

Time-point deletion rebuilds from surviving source constraints, not from cached implied distances. Bounds supported through a removed point can therefore become weaker or unbounded. This is source retraction, not variable elimination preserving the original network’s consequences on surviving points. Re-adding a deleted label with add_time_points/3 creates an unconstrained point; its former incident sources are not restored.

try_add_constraints(STN0, Constraints, Ids, Outcome) returns either:

consistent(STN)
inconsistent(cycle(Sources, TotalWeight))

Ids corresponds to the candidate batch in input order, even when rejected. The cycle’s identified source constraints form an ordered closed directed path with negative total weight. It can contain both existing sources and candidate sources. The original state is unchanged in either case. The consistent-only insertion predicates fail for the inconsistent outcome.

distance(STN,X,Y,Upper,Path) returns one ordered source-constraint path supporting a finite distance. It fails when the pair is unreachable, while distance/4 returns positive_infinity. Identity queries have distance zero and an empty path. With integer weights, the path’s weights sum exactly to the distance. Equal-weight ties retain the earlier selected witness.

A Temporal ATMS can map source IDs to assumption supports and use a cycle’s supports to justify a contradiction. Mutually exclusive assumption environments must be instantiated separately, or handled by a future explicitly labelled distance algorithm. Retaining all sources is essential for replay and retraction; returning one path is not an enumeration of all ATMS labels.

Precedence and interval views

For feasible Y - X bounds [Lower,Upper], can_precede(STN,X,Y) succeeds when Upper is positive or unbounded: some schedule has X < Y. must_precede/3 requires a positive Lower: every schedule has X < Y. The non-strict variants use non-negative bounds. Strict self-precedence fails, while non-strict self-precedence succeeds.

window_relation/4 classifies two marginal uncertainty envelopes, not two events. For example, two time-points constrained to be simultaneous can both have window [0,2]; their envelope relation is equal, but their instants cannot strictly precede each other. Unconstrained points with those same windows could occur in either order. Marginal envelopes omit correlations.

window_interval(STN,Point,Interval) exports one such envelope as i(Start,End), with finite numeric bounds and Start < End. It fails for unbounded or singleton windows, including the singleton reference window. It exports an uncertainty envelope, not an event duration.

event_interval(STN,StartPoint,EndPoint,Interval) exports a concrete event as i(Start,End). Both endpoints must have finite singleton absolute bounds and the duration must be strictly positive. Unknown points, invalid states, uncertain or unbounded endpoints, and reversed or zero-duration events fail. Both exports preserve computed endpoint numeric representations and leave the state and source identifiers unchanged.

event_relation(STN,Start1,End1,Start2,End2,Relation) instead requires all four endpoints to have finite singleton absolute bounds, and each event to have positive duration. Both views jointly rank their four endpoints by arithmetic value and delegate to interval::new/3 and interval::relation/3. Shared ranks preserve arithmetic equality, including equality between an integer and a float, without converting integers to floats. This avoids using the interval object’s term ordering as numeric ordering. Ranked interval terms are internal to the query and are not exported coordinates.

The exported i/2 descriptors contain actual numeric coordinates, not internal ranks. They use arithmetic endpoint ordering and are plain numeric data, not a portable replacement for the ranked interval bridge. In particular, do not assume they can be passed directly to term-order-based interval predicates across backends and mixed numeric representations. Use window_relation/4 or event_relation/6 for portable Allen comparisons.

Relationship to interval constraint networks

The intervals library already provides interval_constraint_network for qualitative temporal reasoning. Its network infrastructure overlaps with this library, but the two solvers address different constraint languages:

Aspect

Interval constraint network

STN

Nodes

Symbolic intervals

Numeric time-points

Constraints

Allen relation sets, such as [before, meets]

Difference bounds, such as time(Y) - time(X) =< 5

Propagation

Relation composition and intersection

Numeric addition and minimum

Contradictions

Empty relation sets

Negative-weight cycles

Results

Qualitative relations and explanations

Numeric bounds, schedules, source-based witnesses

Allen relation-set propagation composes the relations along a path and intersects the result with the existing pair constraint. STN closure instead adds numeric path weights and selects tighter upper bounds. Delegating STN closure to the qualitative solver would lose metric information: an Allen relation alone cannot express a specific duration, deadline, or numeric gap.

The consistency guarantees also differ. Path consistency is not a complete satisfiability test for arbitrary disjunctive Allen networks. In particular, interval_constraint_network::consistent/1 checks that explicit pair relation sets are non-empty; propagation must be requested separately. For an ordinary STN, absence of negative cycles establishes feasibility in exact arithmetic. This library performs that check when constructing states; stn::consistent/1 recognizes library-produced states rather than recomputing their consistency. Floating-point limitations still apply.

Node management, dense indexed storage, immutable updates, and explanation bookkeeping have similar implementation patterns. These are candidates for shared utilities, but do not make the two propagation operations interchangeable or by themselves justify a shared solver abstraction. Concrete Allen classification already delegates to interval, rather than duplicating its relation algebra.

Future symbolic uncertain-event relation networks should build on interval_constraint_network, reusing its refinement, propagation, and explanation APIs instead of implementing another Allen constraint-network solver inside stn. The absence of an uncertain Allen solver noted below is a limitation of this STN library, not of the repository as a whole.

Combining qualitative interval constraints with metric endpoint constraints would still require an explicit bridge. Independently propagating the two networks does not establish their joint consistency. The intended boundary is therefore to keep STN as the metric solver, retain its interval predicates as adapters, and investigate shared indexing or storage utilities separately.

Examples

Anchor a point to a finite window:

| ?- stn::new([t], STN0),
     stn::add_constraints(STN0, [constraint(zero,t,10), constraint(t,zero,-5)], STN),
     stn::bounds(STN, t, Earliest, Latest).
Earliest = 5, Latest = 10.

Export a mixed-representation numeric window:

| ?- stn::new([t], STN0),
     stn::add_constraints(STN0, [constraint(zero,t,2), constraint(t,zero,-1.0)], STN),
     stn::window_interval(STN, t, Interval).
Interval = i(1.0,2).

Export a fixed event’s actual numeric coordinates:

| ?- stn::new([start,end], STN0),
     stn::add_constraints(STN0, [
       constraint(zero,start,1.0), constraint(start,zero,-1.0),
       constraint(zero,end,2), constraint(end,zero,-2)
     ], STN),
     stn::event_interval(STN, start, end, Interval).
Interval = i(1.0,2).

Constrain A’s duration, anchor its start, and require A to end no later than B starts. The precedence edge runs from B’s start to A’s end:

| ?- stn::new([start_a,end_a,start_b,end_b], STN0),
     stn::add_constraints(STN0, [
         constraint(start_a,end_a,10), constraint(end_a,start_a,-5),
         constraint(zero,start_a,2), constraint(start_a,zero,0),
         constraint(start_b,end_a,0), constraint(zero,start_b,20)
     ], STN),
     stn::bounds(STN, start_a, Earliest, Latest),
     stn::must_precede_or_equal(STN, end_a, start_b),
     stn::window_relation(STN, start_a, start_b, Relation).
Earliest = 0, Latest = 2, Relation = before.

Here before describes the start-point envelopes. B’s end remains unbounded, and event_relation/6 would fail because the event endpoints are not fixed. Fixing two events to [0,2] and [2,4] permits an actual meets classification:

| ?- stn::new([sa,ea,sb,eb], STN0),
     stn::add_constraints(STN0, [
         constraint(zero,sa,0), constraint(sa,zero,0),
         constraint(zero,ea,2), constraint(ea,zero,-2),
         constraint(zero,sb,2), constraint(sb,zero,-2),
         constraint(zero,eb,4), constraint(eb,zero,-4)
     ], STN),
     stn::event_relation(STN, sa, ea, sb, eb, Relation).
Relation = meets.

Inspect a conflict without losing its source IDs:

| ?- stn::new([a,b], STN0),
     stn::try_add_constraints(STN0,
         [constraint(a,b,1), constraint(b,a,-2)], Ids, Outcome).
Ids = [1,2],
Outcome = inconsistent(cycle(Sources, -1)).

Sources contains constraint(1,a,b,1) and constraint(2,b,a,-2) in closed-path order. Cycle starting points may depend on the network’s declared node and source order. They do not affect the conflict’s meaning.

Remove an intermediate point and retract its incident sources. The surviving direct constraint is weaker than the original path through the removed point:

| ?- stn::new([a,b,c], STN0),
   stn::add_constraints(STN0, [
     constraint(a,b,3), constraint(b,c,2), constraint(a,c,10)
   ], STN1),
   stn::distance(STN1, a, c, Before),
   stn::remove_time_points(STN1, [b], STN),
   stn::time_points(STN, TimePoints),
   stn::distance(STN, a, c, After).
Before = 5, TimePoints = [zero,a,c], After = 10.

Generate a schedule with a positive anchor and a disconnected negative edge:

| ?- stn::new([anchor,a,b], STN0),
   stn::add_constraints(STN0, [
     constraint(anchor,zero,-5), constraint(zero,anchor,10),
     constraint(a,b,-2)
   ], STN),
   stn::schedule(STN, Schedule).
Schedule = [time(zero,0),time(anchor,5),time(a,5),time(b,3)].

Limitations

  • Numeric domain and precision. Only finite integers and floats are accepted as weights. Symbolic infinities are output bounds, not admissible weights. Native numeric infinities and NaNs are rejected where supported by the backend; rational or other numeric types are not accepted. Integer computations are exact within backend arithmetic limits. Mixed numeric arithmetic and floats can lose precision through rounding, cancellation, underflow, and accumulation. This affects bounds, zero comparisons, negative-cycle detection, and witnesses. There is no implicit epsilon or exact-real guarantee for floating-point results. Prefer suitably scaled integers when conflicts must soundly justify ATMS nogoods.

  • Numerical diagnostics. Arithmetic evaluation, overflow, and backend representation errors propagate; they are not temporal contradictions. A non-finite computed sum raises evaluation_error(float_overflow). Contradictory numerical diagnostics, such as a detected cycle whose reconstructed weight is not negative, a negative closure diagonal after the consistency check, a cyclic witness reconstruction, or a generated schedule violating a source inequality after normalization, raise evaluation_error(stn_numerical_inconsistency). Float path/cycle sums can differ with evaluation order. No automatic rescaling, tolerance, numerical repair, or complete detection of floating-point inaccuracies is provided.

  • Expressiveness. Stored constraints are closed, non-strict difference inequalities over real-valued time. No strict stored inequalities, disjunctive temporal constraints, contingent durations (STNUs), resource constraints, or optimization are provided. Strict precedence queries do not insert strict constraints. A cutoff policy and its current-time assumptions must be supplied by the caller.

  • Reference and unboundedness. zero is reserved, fixed at zero, and cannot be supplied to new/2, removed, or replaced by the caller. Points are not implicitly non-negative. Absolute bounds can be one-sided or completely unbounded; callers must handle symbolic infinities explicitly. Time-point labels must be declared, distinct, and ground. Numeric label identity differs from numeric value equality. Cyclic terms are not supported inputs.

  • Qualitative views. window_relation/4 requires finite non-degenerate windows and describes only marginal envelopes. It cannot establish possible or entailed Allen relations between uncertain events and omits joint endpoint correlations. event_relation/6 requires four finite fixed endpoints and positive durations. Both views fail for zero-duration intervals and unbounded endpoints. There is no event registry or uncertain Allen relation solver.

  • Numeric interval exports. window_interval/3 and event_interval/4 export only finite, non-degenerate numeric i/2 descriptors, not internal ranks or certified term-ordered interval values. Mixed integer/float coordinates must not be assumed compatible with term-order-based interval operations on every backend. These exports do not add uncertain-event relation solving, event registration, zero-duration intervals, or support for unbounded descriptors. Numeric precision limitations still apply.

  • Schedule selection. schedule/2 returns one deterministic assignment, not all schedules, an optimal assignment, or a unique or globally earliest solution. earliest_schedule/2 provides a componentwise earliest assignment only when every point has a finite lower bound; it fails otherwise rather than introducing floors or ignoring unbounded points. Its minimality guarantee is for exact arithmetic, not approximate floating-point results. Neither predicate enumerates schedules or optimizes general objectives. Times are not implicitly non-negative, and finite choices for unbounded points do not make their windows bounded. Floating-point normalization can lose differences; a failed source check raises a numerical diagnostic rather than returning an invalid assignment. Passing the check uses backend arithmetic, not exact-real certification. There is no automatic retry with another assignment, rescaling, or execution policy.

  • Witness completeness. Only one deterministic supporting path or negative cycle is returned. Witnesses need not be minimal conflicts or minimal supports, and alternatives, all cycles, all minimal inconsistent subsets, and all minimal nogoods are not enumerated. ATMS labels, assumption mapping, and conflict minimization belong to the caller. A single merged STN cannot represent mutually exclusive environments.

  • Identifiers and states. Source IDs are unique only along an accepted state lineage, not across independent networks or forks. Rejected IDs can coincide with subsequent allocations from the unchanged input state. States are opaque; constructing or altering their internal terms, or assuming a stable serialization format, is unsupported. consistent/1 recognizes library-produced states; it does not recompute or certify an arbitrary hand-built graph or closure.

  • Point deletion. Removing a time-point also retracts all its incident source constraints. It does not perform variable elimination preserving implied bounds between surviving points, which can consequently weaken or become unbounded. Re-adding a removed label does not restore its former constraints. The reference point zero cannot be deleted.

  • Performance and backend limits. The closure is dense, using O(n^2) cached cells plus O(m) retained sources for n time-points (including zero) and m constraints. Floyd-Warshall takes O(n^3) cell operations. This first implementation uses linear node lookup and list-based Bellman-Ford labels, yielding O(n^2 m) worst-case consistency work. Updates, source retractions, and point additions or deletions rebuild once; there is no incremental O(n^2) update guarantee. A cached pair cell is accessed in constant time after indexing, but each public call also traverses the ground state and uses linear node lookup; query cost is not constant in network size. Witness extraction is linear in path length after validation. schedule/2 scans O(n^2) cells, while earliest_schedule/2 scans O(n) reference-column cells. Both check m sources using linear label lookup. Including full state traversal, each takes O(n^2 + nm) work and O(n) temporary storage in addition to the existing state. Multiple retained snapshots increase live memory use. Matrix dimensions are subject to backend compound-arity and memory limits. Intended for small-to-medium networks, not a large-scale or latency-sensitive solver.

  • Verification scope. Bounded exhaustive fixtures and generated tests are not proofs of correctness or exhaustive checks over all networks or floating-point behavior.